THAT Council receive Staff Report CSOPS.24.018, entitled “125 Peel Street South Servicing Public Information Centre Follow-up”;
AND THAT Council receive the “125 Peel Street South Servicing Public Information Centre #1 Presentation included as Attachment 1 and Follow-up Summary included as Attachment 2;
AND THAT Council direct Staff to proceed with the design and construction of Peel St South with the Level of Service as described in Servicing Alternative A: Fully service Peel St S (water, wastewater, 3rd party utilities) with watermain replacement only on Alice St and Baring St;
AND THAT Council direct Staff to proceed with Peel St S Cross-section Alternative 2: Full Urban Cross-section and Multi-use Trail;
AND THAT Council direct Staff to replace the deficient watermain on Alice St with Cross-section Alternative 2: Existing rural cross-section (restoration of disturbed areas) including drainage improvements and intersection improvements at the Alice St and Lansdowne St intersection;
AND THAT Council direct Staff to replace the deficient watermain on Baring St with Cross-section Alternative 2: Existing rural cross-section (restoration of disturbed areas) as per Baring St Alternative 1 including drainage improvements and intersection improvements at the Baring St and Peel St S intersection;
AND THAT Council approve increasing the engineering contingency by $100,000 to allow for Legal surveying and other miscellaneous costs.