THAT Council receive Staff Report CSOPS.23.011, entitled “Craigleith WWTP Sewage Pumping Station Class EA PIC 2 Follow-up and Notice of Completion for their information”;
AND THAT Council endorse Alternative C as the preferred option to address the 300mm jumper sewer. This includes a new trunk gravity sewer on Long Point Road and new pumping station located at the Craigleith Wastewater Treatment Plant;
AND THAT Council endorse Alternative B as the preferred option to address the septic and leachate receiving station. This includes relocating the septic and receiving station to the Craigleith Wastewater Treatment Plant;
AND THAT Council approve the issuance of the “Notice of Completion” for the 30-day review for the Craigleith WWTP Sewage Pumping Station Class EA.